Preliminary Estimated Construction Cost
| Description | Amount (RM) |
|---|---|
| 1. Main Building Works (2,100 m² × RM2,700 m²) | RM5,670,000 |
| 2. External Driveway / Carparks | RM100,000 |
| 3. Drainage, Water Supply & Sewerage Works | RM80,000 |
| 4. Perimeter Fencing & Gates (2,800 m × RM250.00 m) | RM70,000 |
| 5. Refuse Chamber, Meter Compartment | RM30,000 |
| Preliminaries | RM297,500 |
| Total Estimated Cost | RM6,247,500 |